【全鋼防靜電地板安裝】全鋼防靜電地板施工 全鋼防靜電地板安裝方法
全鋼防靜(jing)電地板安裝方法(fa)
一、施工前準備工作
1、施工(gong)(gong)應做如(ru)下準備(bei)工(gong)(gong)作:熟悉設計施工(gong)(gong)圖紙和勘察施工(gong)(gong)現場(chang)。制定施工(gong)(gong)方案,繪制防靜電地(di)(di)(di)面接(jie)地(di)(di)(di)系統(tong)圖、接(jie)地(di)(di)(di)端子(zi)圖和地(di)(di)(di)網(wang)布置圖。備(bei)齊各(ge)種(zhong)施工(gong)(gong)材(cai)料(liao)、設備(bei)、器具(ju),并(bing)(bing)檢驗合格。徹底清(qing)除施工(gong)(gong)場(chang)地(di)(di)(di)、器具(ju),并(bing)(bing)檢驗合格。徹底清(qing)除施工(gong)(gong)場(chang)地(di)(di)(di)的(de)塵土(tu)、小沙(sha)石等影響工(gong)(gong)程質量(liang)的(de)殘留物(wu)。大(da)于140平方(fang)米的工(gong)程,應(ying)作樣鋪(pu)設。
2、施工(gong)(gong)場(chang)地應(ying)符合下列要求(qiu):基層地面(mian)(mian)無論是水(shui)泥(ni)地面(mian)(mian)、水(shui)磨石地面(mian)(mian)或(huo)其(qi)它(ta)硬質(zhi)地面(mian)(mian),都(dou)應(ying)表面(mian)(mian)平整、凹凸不平等必須修補(bu)。對于新建工(gong)(gong)程(cheng)項目(mu),在土建施工(gong)(gong)時應(ying)一(yi)預設(she)接地裝置(zhi)。工(gong)(gong)程(cheng)面(mian)(mian)積(ji)100平(ping)方米以內的設1到2個接地端子。對于老廠房改造項目,應根據實際情況按相同要求確定接地端子位置與數量。應在室內裝修工作已基本完工、安裝與基層上的設備已固定在預定位置、放置在活動地板下的管線或導線已鋪設就位后,方可進行防靜電活動地板安裝,不得上下交叉作業。
二、施工步驟(施工工藝)
1、認真檢(jian)查地面平整度(du)及墻面垂直度(du),如發現有重大缺陷或需要(yao)局(ju)部改造,應(ying)向甲方有關部門提出;
2、拉水平線(xian),并將(jiang)地板安裝(zhuang)高(gao)度用墨線(xian)彈(dan)到墻面上,保證鋪設(she)后的地板在(zai)同一水平內,測(ce)量(liang)室內的長度、寬度及選擇基準(zhun)位置,并在(zai)地面彈(dan)出安裝(zhuang)支座的網絡格(ge)線(xian),以保證鋪設(she)整齊、美(mei)觀,同時盡量(liang)減少(shao)地板的切(qie)割(ge);
3、將要安裝的支座調整到(dao)同一需要的高度并將支座擺到(dao)地面網格線的十字交點處;
4、用安裝螺釘將(jiang)桁(heng)梁(liang)固定到(dao)支座(zuo)上,并(bing)用水平尺、直角尺逐一校正(zheng)桁(heng)梁(liang),使之(zhi)既在(zai)同一平面內(nei),又相互垂直;
5、用(yong)吸板器在組裝好的(de)桁梁(liang)上放置活動地板;
6、若靠近墻面處剩余尺寸小于(yu)活動地板的(de)長度,可以用切割地板的(de)方(fang)法進(jin)行拼(pin)補;
7、在(zai)鋪設地(di)板時,用水(shui)(shui)泡水(shui)(shui)平(ping)儀逐(zhu)塊(kuai)找平(ping),活動地(di)板的(de)的(de)高度(du)靠可調支座調節,鋪設過程中應(ying)輕拿(na)輕放,防止劃傷(shang)地(di)板及損壞(huai)邊(bian)(bian)條,同時應(ying)邊(bian)(bian)鋪設邊(bian)(bian)打掃,避免將雜物、灰塵遺留(liu)在(zai)地(di)板下面;
8、在機房設置較重設備(bei)時,可(ke)在設備(bei)基座(zuo)的地板下加裝支座(zuo),以防地板變形;
9、HPL裝飾板需要切割或開(kai)口加(jia)工時(shi),其(qi)開(kai)口凹角處應制φ6~φ8止裂孔,以防止加工后的防靜電地板裝飾面開裂。