【保溫(wen)板施(shi)工(gong)工(gong)藝】保溫(wen)板施(shi)工(gong)工(gong)藝有(you)哪些具體步驟 保溫(wen)板施(shi)工(gong)工(gong)藝步驟
保溫板施工工藝步驟
一、玻化微珠砂漿
1、先將鋼絲網(wang)按預(yu)定尺(chi)寸裁好,長度應斷在分隔縫槽中;
2、在保溫層抹2-3㎜厚的抗(kang)裂(抹面(mian))砂漿,然后用錨栓將鋼(gang)絲網鋪(pu)貼平(ping)整;
3、熱鍍鋅鋼絲網(wang)一般(ban)豎向使用,接頭部位(wei)的搭接寬度不(bu)應(ying)小于5㎝
1、施工準備
基層(ceng)墻體經(jing)過工程驗收達(da)到(dao)質(zhi)量標(biao)準,施工前應將基層(ceng)墻面的灰塵、污垢、油漬等清洗干凈表面達(da)到(dao)平整(zheng)。
2、施工要點
A:無機活性墻體保溫隔熱材料(liao)A級不燃綠色(se)節能產品(pin)(pin)配(pei)置按照產品(pin)(pin)與水重量比1.5:1的(de)比例(li),攪拌(ban)機攪拌(ban)后(hou)放置5-15分鐘達到適宜操(cao)作(zuo)即可。
B:無機活性墻體保溫隔熱(re)材(cai)料A級不(bu)(bu)燃(ran)綠(lv)色節能產(chan)品(pin)使(shi)用(yong)(yong)先(xian)用(yong)(yong)清水(shui)將(jiang)(jiang)基(ji)(ji)面(mian)(mian)(mian)墻(qiang)(qiang)面(mian)(mian)(mian)的灰塵和油污處理(li)干(gan)凈并達到(dao)適度(du)濕(shi)潤(run)后(hou),將(jiang)(jiang)攪拌好的產(chan)品(pin)直接批(pi)抹(mo)于基(ji)(ji)層(ceng)墻(qiang)(qiang)體上或已施(shi)工(gong)過的水(shui)泥(ni)砂漿面(mian)(mian)(mian)上。第一(yi)(yi)遍(bian)(bian)均(jun)勻密實將(jiang)(jiang)墻(qiang)(qiang)體覆蓋,厚度(du)在10mm左(zuo)(zuo)右,當第一(yi)(yi)遍(bian)(bian)材(cai)料的含水(shui)率大約(yue)在50%時,可(ke)(ke)進行(xing)第二遍(bian)(bian)批(pi)抹(mo),批(pi)抹(mo)厚度(du)掌握在10-20mm之間。達到(dao)粘(zhan)結牢固、不(bu)(bu)空鼓、不(bu)(bu)開裂。一(yi)(yi)般(ban)產(chan)品(pin)施(shi)工(gong)厚度(du)在20mm內可(ke)(ke)一(yi)(yi)次性批(pi)抹(mo)完成(cheng)(cheng),產(chan)品(pin)厚度(du)在30mm內可(ke)(ke)二次批(pi)抹(mo)完成(cheng)(cheng),也(ye)可(ke)(ke)做(zuo)內外復合施(shi)工(gong),既(ji)可(ke)(ke)省(sheng)掉內外粉刷水(shui)泥(ni)砂漿的材(cai)料成(cheng)(cheng)本費用(yong)(yong)和人工(gong)費,又(you)可(ke)(ke)節省(sheng)施(shi)工(gong)工(gong)期,達到(dao)一(yi)(yi)舉(ju)多得。初凝時間為2小時左(zuo)(zuo)右,全部(bu)工(gong)序當天完成(cheng)(cheng),七天后(hou)便(bian)(bian)可(ke)(ke)粘(zhan)貼面(mian)(mian)(mian)磚,十天后(hou)便(bian)(bian)可(ke)(ke)做(zuo)涂料飾面(mian)(mian)(mian)。若基(ji)(ji)層(ceng)墻(qiang)(qiang)體為混凝土剪(jian)力(li)墻(qiang)(qiang)時,使(shi)用(yong)(yong)產(chan)品(pin)需提前一(yi)(yi)天做(zuo)常規界面(mian)(mian)(mian)砂漿甩(shuai)漿處理(li),建議(yi)剪(jian)力(li)面(mian)(mian)(mian)接逢(feng)處掛(gua)網(玻纖網或鍍(du)鋅(xin)鋼絲網),以緩解基(ji)(ji)層(ceng)墻(qiang)(qiang)體材(cai)料因澎脹收縮系數不(bu)(bu)同而出現問題。
C:質量檢驗(yan)基層墻(qiang)體及保溫(wen)層施工(gong)達(da)到相關標(biao)準要(yao)求(qiu),各構(gou)造層之間必須粘結牢固(gu)、無(wu)脫層、無(wu)空鼓、無(wu)裂(lie)縫等現象。
三、施工流程
外墻外保溫或外墻內保溫涂料飾面和面磚飾面工藝流程:基層處理(混凝土等光面墻體需使用常規界面砂漿)→套方、吊垂直、彈控制線、沖筋、做口、復驗→批抹產品→彈分格線、開分格槽、嵌貼滴水槽→涂料(面磚)飾面。