一、電力施工許可證辦理條件
(1)施(shi)工(gong)現場(chang)基本(ben)符合施(shi)工(gong)條件;
(2)已對施工(gong)現場(chang)的審批程序進行了辦理;
(3)已獲(huo)得城市規劃(hua)區建設(she)項目的規劃(hua)許可;
(4)如(ru)果(guo)需要拆除,拆遷進度(du)應符合施工要求;
(5)已確定施(shi)工企業;按(an)照規定委托(tuo)監理的項目委托(tuo)監理單位。
(6)施工(gong)圖紙符合相關設(she)計規(gui)范的要求(qiu);
(7)質(zhi)量監(jian)督部(bu)門(men)和安(an)(an)監(jian)部(bu)門(men)辦理了相應質(zhi)量、安(an)(an)全監(jian)督注冊手(shou)續;
(8)建(jian)(jian)設資(zi)金已經落實,如(ru)果建(jian)(jian)設期(qi)不(bu)足一(yi)年,現(xian)有資(zi)金不(bu)得低于(yu)項目(mu)合同(tong)價(jia)格的50%;如(ru)果建(jian)(jian)設期(qi)超過一(yi)年,現(xian)有資(zi)金不(bu)得低于(yu)項目(mu)合同(tong)價(jia)格的30%。
二、電力施工許可證辦理材料
(1)《建筑工(gong)(gong)程施(shi)工(gong)(gong)許可證申請表》(施(shi)工(gong)(gong)單位可以填寫系(xi)統(tong)并通過(guo)系(xi)統(tong)下載(zai)打印(yin));
(2)建設用(yong)(yong)地批準手續序(國有土地使用(yong)(yong)證(zheng)、國有土地使用(yong)(yong)權(quan)出讓(rang)批準書、建設用(yong)(yong)地批準或建設用(yong)(yong)地規(gui)劃許可等(deng));
(3)建設工程規(gui)劃許可;
(4)中標通知(按規定直接發放的項目,應提供直接合同備案表(biao));
(5)施工(gong)合(he)同備案表(或加(jia)蓋印章的施工(gong)合(he)同);
(6)施工(gong)圖設計文件的合格證書;
(7)建設工程質量監督登記(ji)表;
(8)建筑工程安全(quan)監(jian)察登(deng)記表;
(9)施工項目監理合同;
(10)建設資(zi)金到位(wei)證(zheng)明;
(11)建設單位發(fa)出無拖(tuo)欠工程款情形承諾書。
三、如何申請電力施工許可證
根(gen)據電廠的(de)位置(zhi),到(dao)相應(ying)的(de)管(guan)轄地方的(de)對應(ying)機構去辦理即可。根(gen)據《建(jian)筑法》的(de)有關規(gui)定(ding),“建(jian)設行政主管(guan)部門應(ying)當自收到(dao)申(shen)請之(zhi)日(ri)(ri)起十五(wu)日(ri)(ri)內,對符合條件的(de)申(shen)請頒發(fa)施工許可證。”加上資料準備和提交時間大概需(xu)要(yao)1個月(yue)左右。